Wastney Terrace Stormwater Upgrade
Protecting homes. Respecting neighbours.
Project Overview
Client Nelson City Council
Location Wastney Terrace, Marybank, Nelson
Service Stormwater Infrastructure
Project Value $1.87M
Duration April 2022 – July 2023
Completed 2023
-
530m reinforced concrete stormwater network
Constructed through private property and steep terrain
21 manholes and two high-capacity sumps
Deep excavations with temporary structural support
Additional works delivered through collaborative procurement
Zero Lost Time Injuries (LTIs)
-
The Wastney Terrace Stormwater Upgrade was designed to improve flood resilience for the Marybank community by constructing a new stormwater network through steep terrain, private driveways and residential properties before discharging to the coast.
The project required more than technical capability. A new 530-metre reinforced concrete pipeline, incorporating 21 manholes and high-capacity stormwater structures, had to be installed while relocating existing water and wastewater services and working within metres of occupied homes. Every stage of construction demanded careful planning to protect private property, existing structures and the relationships that would ultimately determine the project's success.
The project presented far more than a conventional pipeline installation. The proposed alignment crossed an operational school, a former landfill site, busy public roads, recreational facilities and existing underground services. The original construction methodology also relied on long directional drill installations, introducing significant technical, financial and programme risk before construction had even begun.
-
For many residents, construction wasn't taking place outside their property—it was happening through it.
Maintaining access, protecting homes and communicating openly with landowners became just as important as installing the new infrastructure. The project also presented significant environmental challenges, with steep topography, deep excavations and severe weather events requiring robust erosion and sediment controls throughout construction. Success depended on earning trust as much as delivering engineering excellence.
-
Tasman Civil worked closely with Nelson City Council throughout an extensive direct procurement process, helping refine multiple design iterations before construction commenced. That collaborative approach continued on site, allowing the team to respond confidently as additional work packages were introduced and project priorities evolved.
Technically, the project required deep excavations, groundwater management and temporary support systems to safely construct new stormwater infrastructure immediately beside existing homes and structures. Careful engineering assessments, structural monitoring and tailored construction methodologies ensured neighbouring buildings remained stable throughout the works, despite excavation occurring within close proximity to occupied dwellings.
Equally important was the team's commitment to stakeholder relationships. Regular communication, respectful engagement and practical problem solving helped build strong relationships with residents, landowners and neighbouring property owners. That trust not only contributed to a successful project outcome but also led to new opportunities beyond the contract itself.
-
The completed stormwater network provides greater resilience for the Marybank community, reducing flood risk while delivering modern infrastructure designed to support the area's future.
Completed safely and below the client's original budget expectations, the project also earned positive feedback from residents and property owners for the way the works were managed. It stands as an example of Tasman Civil's belief that successful infrastructure projects are measured not only by the assets delivered, but by the relationships built throughout the journey.
-
Stormwater Infrastructure
Deep Excavations
Reinforced Concrete Pipelines
Temporary Works
Structural Support Systems
Service Relocations
Erosion & Sediment Control
Stakeholder & Landowner Engagement
Collaborative Contract Delivery
Quality Assurance
Environmental Management